Air venting has been delayed and is scheduled to begin this week. This is likely to cause some distrurbance, and will occur during daylight hours. The second pipeline is being drilled at a rate of 100 - 150m per day and remains ahead of schedule. Due to Health and Safety Reasons it will be necessary to close Cockleton Lane for 7-10 days from 21st March. I've asked that the contractors continue to ensure residents are kept fully informed about this, and in the meantime I applaud Rew Street residents for the patience so far.
The deadline for completion is 12th July, with the fields being reseeded and restored during this Autumn.
The next meeting is due to be held early March. Due to the imminent closure of Cockleton Lane, I've asked that Gurnard Pines attends as well as a representative from Gurnard School. If you have any complaints, let me know so that I can let the contractors know!